We are renovating the tennis courts in the Willows!

Finley Asphalt is doing significant repairs to the Clubhouse and Calabash courts.

The tennis court project includes partial excavation to expose and improve sections of the court subbase.  Once the asphalt is replaced, it requires thirty (30) days to cure before application of an upgraded cushioned color coat.  The work began just after September 1.  While it should take about ninety (90) days from beginning to end, weather plays a major role.  It is possible the final color coat will not be able to be applied until Spring.   Finley will draw temporary lines on the asphalt if they find the weather is significantly delaying application of the color coat.

We appreciate your patience as this important project is in progress.